5.4. Scheduling Lead Times and Delivery
A. The Work shall be conducted based on the following sequence and lead times:
- Schedule starts after PO's are released to FSEC.
- Submittals and Shop Drawing Lead Time to produce: Typical 2 weeks.
- Shop Drawing Review by General Contractor/Architect/Consultant: Typical 2 weeks.
- Rough ins completed by trades, stub up locations.
- Field Measure millwork: Typical 1-2 days.
- Install millwork: Typical 2 weeks – this varies depending on project size
- Template Counter Tops: Typical 1-2 days.
- FSEC Partial Installation: Typical 1 week – this varies depending on project size
- Install Countertop: Typical 1-3 days – this varies depending on project size
- FSEC Final Installation: Typical 1 week – this varies depending on project size
- MEP Trades to make final connections.
B. Delivery: Coordinate with progress of construction and Owner's operation schedules. Unless otherwise instructed and documented by Owner or General Contractor, the following procedures apply:
- Field-Assembled Fixed Equipment: Integrated into the structure; including, but not limited to, walk-in box assemblies, exhaust hoods, drain trench or grate assemblies, conveyor systems, and ceiling mounted utensil racks are to be sent to the job-site when directed by the General Contractor and installed or protected accordingly.
- All other Fixed Equipment: Deliver after completion of adjacent finished ceilings, lighting, finished floor and wall systems; including painting.
- Major Movable Equipment: Deliver when possible to inventory in a secured area for the interim job site storage or, if secured storage is not available, when fixed equipment installation and clean-up has been completed.