5.4. Scheduling Lead Times and Delivery


A. The Work shall be conducted based on the following sequence and lead times:

  1. Schedule starts after PO's are released to FSEC.
  2. Submittals and Shop Drawing Lead Time to produce: Typical 2 weeks. 
  3. Shop Drawing Review by General Contractor/Architect/Consultant: Typical 2 weeks.
  4. Rough ins completed by trades, stub up locations.
  5.  Field Measure millwork: Typical 1-2 days.
  6. Install millwork: Typical 2 weeks – this varies depending on project size
  7. Template Counter Tops: Typical 1-2 days. 
  8. FSEC Partial Installation: Typical 1 week – this varies depending on project size
  9. Install Countertop: Typical 1-3 days – this varies depending on project size
  10.  FSEC Final Installation: Typical 1 week – this varies depending on project size
  11. MEP Trades to make final connections.  
B. Delivery: Coordinate with progress of construction and Owner's operation schedules. Unless otherwise instructed and documented by Owner or General Contractor, the following procedures apply:

  1. Field-Assembled Fixed Equipment: Integrated into the structure; including, but not limited to, walk-in box assemblies, exhaust hoods, drain trench or grate assemblies, conveyor systems, and ceiling mounted utensil racks are to be sent to the job-site when directed by the General Contractor and installed or protected accordingly. 
  2. All other Fixed Equipment: Deliver after completion of adjacent finished ceilings, lighting, finished floor and wall systems; including painting. 
  3. Major Movable Equipment: Deliver when possible to inventory in a secured area for the interim job site storage or, if secured storage is not available, when fixed equipment installation and clean-up has been completed.